Permit Drawings in San Diego: Review and Approval Timeline

  • Writer: Seth Gilley
    Seth Gilley
  • Oct 7
  • 11 min read
Permit Drawings in San Diego: Review and Approval Timeline

Key Highlights

  • Understanding the San Diego permitting process is key to avoiding costly project delays.

  • The average processing time for building permits varies, with 61% of all permits approved within one week, but complex residential projects often take longer.

  • Permit approval timelines in the City of San Diego depend heavily on project complexity and the completeness of your submission.

  • Submitting accurate and detailed permit drawings is the best way to speed up the plan review process.

  • Resources like the Development Services Department dashboard provide current timeline estimates.


How long does it typically take to get permit drawings reviewed and approved in San Diego?

Starting a construction or remodeling project in San Diego is an exciting venture. However, before you can break ground, you need to navigate the permitting process. This essential step involves getting your project plans, or permit drawings, reviewed and approved by the City of San Diego's Development Services Department.


Understanding the timeline and what to expect can make the difference between a smooth start and frustrating delays.


This guide will walk you through the review and approval process, helping you plan your project more effectively.


Overview of Permit Drawings in San Diego


Permit Drawings in San Diego

When you submit permit applications in San Diego, your permit drawings are the centerpiece of your submission. These detailed plans communicate your project's scope to the City of San Diego, ensuring it meets all safety and zoning requirements.


Navigating the local regulations is a critical part of the process. Your drawings must demonstrate full compliance with building codes to gain approval. Let's look closer at what these drawings entail and why they're so important.


Definition and Importance of Permit Drawings

So, what exactly are permit drawings? They are detailed architectural and engineering plans that illustrate every aspect of a proposed construction project. Think of them as the official blueprint for your build. These documents show everything from structural layouts and electrical plans to plumbing systems and land use details.


These drawings are necessary because they serve as the primary tool for the city to verify your project's safety and compliance. They provide tangible proof that your plans adhere to all local building codes and zoning regulations. Without them, reviewers would have no way to assess the project's integrity or its impact on the surrounding area.


Ultimately, permit drawings protect you, your property, and the community. They ensure that construction is performed correctly and safely, preventing potential hazards and ensuring the final structure is sound. Getting your building permits depends entirely on the quality and accuracy of these plans.


Types of Projects Requiring Permit Drawings

You might be wondering if your specific project needs permit drawings. In San Diego, most construction work beyond simple cosmetic updates requires a permit and, therefore, detailed drawings. This applies to both residential and commercial projects.


Generally, you will need to submit permit drawings for projects such as:

  • Constructing new homes or commercial buildings

  • Room additions and major remodels

  • Installing solar panels or new HVAC systems


The processing timelines can differ significantly between project types. Commercial projects often involve more complex systems and stricter regulations, leading to longer review periods compared to most residential jobs. Likewise, simple site preparation may move faster than a complex new build. Understanding your project's category helps set realistic timeline expectations from the start.


Role of Permit Drawings in Construction Approval

Permit drawings are the foundation of the construction approval process in San Diego. When you submit your application, these plans go to the Development Services Department for a thorough plan review. Officials from various divisions will scrutinize your drawings to ensure every detail complies with current codes and regulations.


Does submitting complete and accurate drawings speed up the approval process? Absolutely. In fact, it's the single most effective way to avoid delays. When your drawings are clear, comprehensive, and correct, reviewers can quickly verify compliance without needing to send them back with questions or correction notices. This smooths out the entire permit process.


An incomplete or inaccurate submission, on the other hand, brings the approval process to a halt. It triggers requests for more information, leading to revisions and resubmissions that can add weeks or even months to your timeline. Taking the time to get your drawings right from the beginning saves you time and frustration later.


The Review and Approval Process Explained

The permit process in the City of San Diego is a structured sequence of steps designed to ensure all construction is safe and compliant. Once you submit your permit drawings San Diego, they enter the plan review stage, where city officials evaluate them against a checklist of requirements.


Understanding this journey from submission to approval is crucial for managing your project timeline. Let's break down how to submit your drawings, which departments are involved, and what documentation you'll need to secure your building permits.


Step-by-Step Breakdown of Permit Drawing Submission


Step-by-Step Breakdown of Permit Drawing Submission in San Diego

Submitting your permit applications to the City’s Development Services Department is primarily done online through the Accela Citizen Access Portal. This streamlined system helps manage the flow of projects seeking the necessary permits.


The general submission process involves these key actions:

  • Create an account on the Accela portal.

  • Fill out the required application forms, like the DS-345 Project Contact Information form.

  • Upload all your digital permit drawings and supporting documents.

  • Pay the initial plan review fees to get your project in the queue.


How long does it take for approval? Timelines vary widely. While the city processes 61% of all permits within a week, larger residential remodels typically fall into the 1-6 month category. Complex projects can take even longer, which is why a complete and accurate submission is so vital to keep things moving.


Key Departments Involved in Review

Your permit drawings don't just go to one person; they are reviewed by multiple divisions within the San Diego Development Services Department. Each department checks the plans for compliance with its specific area of oversight, ensuring a comprehensive review.


Key departments include the Building Division, which checks for structural safety and code compliance, and the Land Use Enforcement Division, which verifies zoning and property line requirements. Depending on your project, other departments may also be involved, such as the Fire-Rescue Department for reviewing fire suppression systems or the Transportation & Storm Water Department.


If your review is taking longer than expected, your first point of contact should be the project manager or reviewer assigned to your case through the city's online portal. You can also contact the Development Services Department's main line at (619) 446-5000 for general inquiries or to be directed to the right department point person.


Typical Documentation Required for Approval

To secure approval, you must submit a complete package of necessary documents along with your drawings. Missing paperwork is a common reason for delays, so it's important to be thorough.


Beyond the main permit drawings, your submission package should typically include:

  • A completed permit application form.

  • Structural calculations and Title 24 energy compliance reports.

  • A site plan showing property lines, setbacks, and existing structures.


Depending on your project's location and scope, you may need additional permits and documentation. For example, projects in areas like La Jolla or Pacific Beach often require a Coastal Development Permit. Once the review is complete and successful, you will need to settle all outstanding permit payments before the final permit is issued.


Factors Impacting Permit Drawing Timelines

Even with a perfect submission, several factors can influence your permit approval timeline. Project complexity is the most significant variable, as more intricate designs require more detailed review and may involve multiple city departments, adding additional time.


Understanding these potential delays is key to managing your expectations during the permitting process. From the scale of your project to the accuracy of your paperwork, each element plays a role in how quickly your permit is issued.


Project Complexity: Residential vs. Commercial

The complexity of your project is a primary driver of the permit approval timeline, and there are distinct differences between residential and commercial projects. Residential permits, especially for smaller remodels or additions, are generally more straightforward and follow a more predictable approval process.


Commercial projects, however, are inherently more complex. They often involve more rigorous structural requirements, fire and life safety systems, accessibility standards (ADA), and potentially more significant land use considerations. This added complexity requires reviews from specialized city departments, extending the overall timeline.


The table below highlights some key differences that affect review times.

Feature

Residential Projects

Commercial Projects

Code Requirements

Standard building codes

Stricter codes, including fire, accessibility (ADA), and health

Structural Review

Simpler for wood-frame construction

Often involves complex steel or concrete structures

System Complexity

Basic electrical and plumbing

Advanced HVAC, fire suppression, and electrical systems

Departmental Reviews

Fewer departments are typically involved

Multiple specialized departments (Fire, Health, etc.)

Common Causes of Delays and How to Avoid Them

Are you looking for ways to spend less time waiting for permit approval? The best strategy is to avoid the common pitfalls that cause delays. Most hold-ups are preventable with proper preparation and due diligence.


The most frequent cause of delays is incomplete submissions. When reviewers need to request additional information or clarification, your project is put on hold until you respond. This back-and-forth can add significant time to your project.


To avoid these delays, focus on:

  • Thorough Preparation: Double-check that all required forms, drawings, and calculations are included before you submit.

  • Adherence to Codes: Ensure your plans are fully compliant with the latest San Diego building codes.

  • Prompt Responses: If the city does request changes, respond as quickly as possible to get your project back in the review queue.


Effects of Incomplete or Incorrect Submissions

Submitting complete and accurate drawings is the fastest way to get your permit, and the opposite is also true. Incorrect submissions can have a ripple effect, causing significant setbacks beyond just lost time.


The most immediate effect is the need for revisions, which requires additional time from your architect or drafting designer and pushes your project to the back of the review line. This delay can lead to unexpected costs, such as having to pay contractors for standby time or fees for rescheduling work.


Furthermore, each revision cycle may incur additional fees from the city for re-reviewing your plans. These extra permit payments can strain your budget. The bottom line is that investing in accuracy upfront saves you from a cascade of problems, ensuring a smoother, more cost-effective path to approval.


Timeline Expectations for Permit Drawing Approval

Setting realistic expectations for your permit approval timeline is crucial for project planning. While everyone hopes for a quick turnaround, the average processing time in San Diego can vary significantly based on the project.


The Development Services Department processes a high volume of applications, and timelines are influenced by workload, project complexity, and submission quality. Data from both the City and County of San Diego can help provide a clearer picture of what to expect.


Average Wait Times for Building Permits in San Diego

For San Diego homeowners, understanding the average wait times for building permits is key to effective planning. According to recent data from the City of San Diego, the average processing time for residential permits was 176 days in 2024. This reflects the time from initial submission to final approval.


It's important to note that this is an average. Some simpler permits, like those for basic site prep, might be approved much faster. The data shows that 15% of residential permits are processed in under a week. However, more substantial projects often fall into longer categories.


Currently, about 40% of residential permits take between one and six months, while 25% take six months or more. This highlights why it is so important for homeowners to submit their applications as early as possible and ensure they are complete to avoid unnecessary delays.


Estimated Processing Duration by Project Type (ADU, Remodels, New Builds)

Your project timeline will be heavily influenced by the type of construction. New builds, remodels, and Accessory Dwelling Units (ADUs) each have their own typical review durations. The ADU permit process, for instance, has been a focus for the city as it works to approve new housing units efficiently.


While the city has streamlined the process, the complexity of ADUs means they often require a thorough review. Major remodels and new builds are even more complex, involving extensive structural, electrical, and plumbing plans that demand in-depth scrutiny from multiple departments.


Here are some general estimates for different project types based on recent data and experience:

Project Type

Estimated Processing Duration

Factors Influencing Timeline

ADU

3 - 5 months

Size, pre-approved plans vs. custom, site conditions

Major Remodels

2 - 8 months

Scope of structural changes, kitchen/bath updates

New Builds

6 - 12+ months

Size of home, site complexity, zoning requirements

Where to Find Current Processing Time Estimates

If you want the most up-to-date information on permit timelines, the City of San Diego provides several valuable resources. Staying informed can help you adjust your project schedule and manage expectations.


The best place to start is the City’s Development Services Department website. They maintain an online dashboard with real-time data on permit processing. This tool provides a transparent look at the department's current workload and approval rates.


For the most recent estimates, be sure to check these resources:

  • The San Diego DSD Permit Dashboard: This offers current and historical data on application volumes and processing times.

  • Information Bulletins: The city periodically releases bulletins, like Information Bulletin 400 for ADUs, which contain specific guidelines and timeline information.

  • Department Point of Contact: Once your project is submitted, your assigned plan reviewer can provide the most accurate estimate for your specific case.


Tips for Accelerating the Permit Drawing Approval Process


Tips for Accelerating the Permit Drawing Approval Process

Waiting for the proper permits can be stressful, but there are proactive steps you can take to spend less time in limbo. Following best practices and being strategic can significantly speed up the approval process, giving you peace of mind.


A smooth process comes down to preparation and communication. By ensuring your submission is flawless and knowing how to navigate potential hold-ups, you can move your project forward more efficiently.


Best Practices for Submitting Complete Drawings

As we've discussed, submitting complete and accurate drawings is the number one way to accelerate your permit approval. The Development Services Department can process a clean, comprehensive application much faster than one that is missing information or contains errors.


To ensure your submission is top-notch, it’s essential to be meticulous. Work with your designer or architect to review every detail before you submit. Make sure your plans are clear, legible, and contain all the necessary information that reviewers will be looking for.


Follow these best practices for a complete submission:

  • Verify that all plans comply with the latest San Diego building codes.

  • Include all necessary documents, such as structural calculations and energy reports.

  • Clearly label all aspects of your drawings, from materials to dimensions.

  • Provide a detailed site preparation plan if required.


Strategies to Minimize Hold-Ups and Expediting Options

Beyond submitting a perfect application, there are other strategies to keep your permit process on track. One effective approach is to hire a professional to manage the process for you. Experienced project managers or permit expediters are familiar with the city's requirements and have established relationships with reviewers.


Hiring an expediter can absolutely speed up approval timelines. These professionals specialize in navigating bureaucracy. They ensure your application is correct before submission, respond quickly to city comments, and can often anticipate issues before they arise, saving valuable time.


Consider these strategies to minimize hold-ups:

  • Hire a Permit Expediter: A professional can manage the entire submission and review process.

  • Prompt Payment of Fees: Pay all invoices immediately to avoid administrative delays.

  • Stay Engaged: Regularly check the status of your application online and follow up with your project manager as needed.


Conclusion

In summary, understanding the permit drawing process in San Diego is crucial for anyone involved in construction projects. By familiarizing yourself with the types of projects that require permit drawings and the comprehensive review and approval timeline, you can effectively navigate potential challenges. Being aware of common delays and proactively taking steps to ensure your submissions are complete will not only expedite the approval process but also lead to a smoother construction journey.


If you have any questions or need assistance, get in touch with Outside the Box, Design & Drafting Services, LLC to help you streamline your permit approvals in San Diego and keep your project on track.


FAQ on Timings for permit drawings reviewed and approved in San Diego


Are permit review times different for residential and commercial submissions in San Diego?

Yes, review times are different. Commercial projects in San Diego typically take longer to approve than residential ones. This is due to their greater complexity, which requires more extensive reviews for compliance with stricter building codes, fire safety, and accessibility standards, lengthening the overall permit process.


Does hiring an expediter or professional speed up approval timelines?

Hiring a permit expeditor or an experienced project manager can definitely speed up the approval process. These professionals are experts in the permitting process and can help avoid common mistakes, ensure complete submissions, and communicate effectively with the Development Services Department, minimizing delays.


Who should I contact if my San Diego permit review takes longer than expected?

If your review is delayed, your first department point of contact should be the plan reviewer or project manager assigned to your case by the City of San Diego. You can find their contact information in the online permit portal. For general inquiries, you can call the Development Services Department directly.

 
 
 